This project consisted of the rehabilitation of waterfront structures at a major Brooklyn park, and included the demolition of 500 linear feet of existing bulkhead and 600 feet of existing pile supported platform. The installation of new pipe pile supported relieving platform was performed as well as the placement of 600 linear feet of Rip Rap and the encasement of existing cribbing with steel sheeting.